Anas & Mido Mother  #190304  Sun, 29 Jan 06 12:00 PM

Hi all;

could you please correcth this for me ( i am in urgent need for it):

Steps of tendering process

1.      Preparing Designs and Tenders documents:

-         The Engineering and consulting firm prepare the designs with co-operation with the beneficiary

-         CRS staff (program manager, project officer, and engineer) discusses the designs and making any necessary changes.

-         Getting the final approval from the beneficiary.

-         Then the engineering firm prepare bill of quantity taking in consideration the budget.

-         Review bill of quantity from CRS staff and making any necessary changes.

-         Photocopy 15 copy from the tender or less.

2.      Advertising & selling tenders:

-         Announce tender advertisement in tow local newspaper for one day or one local newspaper for two days.

-         Send a copy of the advertisement to Contractor Union & engineering syndicate.

-         Sending an invitation letters to 10 or more contractors in project area, in case of closure or any reason which prevent newspaper to reach.

-         Arranging a visit to the project site from the contractors after three days from starting of selling tender, and in this day we stop selling tender for any contractor.

-         After field visit a meeting arranged between CRS staff, consultant office, contractors to answer any questions related to the quantities, designs, etc…….

3.      Opening  tenders & taking the decision:

-         Opening tender session included representatives from ministry of local government, Ministry of interior, municipality, beneficiary, engineering consultant firm, and contractors.

-         Tenders which received after close time is never accepted.

-         After opening tenders the engineers revise the tenders to be sure that all calculations are right and all proper documents are available.

-         Making an overall evaluation for tenders from the engineers (contractors name, prices, degrees, documents……………)

-         Asking about first three contractors reputation from three trusted sources or more (municipality, donor, etc) which contractor has implemented projects for them in last two years.

-         Taking the primary decision and sending it to B.Hanina office with all documents.

-           After B. Hanina office approval, we arrange a meeting of our committee which consists of representatives of interior ministry, local government ministry, municipality, engineering consultant firm, beneficiary to get the final approval for the decision.

-         Sending an acceptance letter for chosen contractor and apology letters for other contractors.

-         Asking the contractor to prepare his guarantees (performance & delay guarantees) during one week

-         Signing the contract.

  
Not Ranked
Joined on Sun, Dec 11 2005
New Member (11)
FloridaMan  #262231  Sun, 03 Sep 06 05:45 PM

OK, Main comment. When you do a list, the grammatical form of each item in the same list must be the same. So if you start the first two items with a verb then all other must start with a verb. And be consisten on your punctuation.  Do not end one with a period and not another.

Engineering and consulting firm prepares the designs with co-operation of the beneficiary

CRS staff (program manager, project officer, and engineer) discusses the designs and makes any necessary changes

Beneficiary gives final approval

Engineering firm prepares the bill of lading taking in consideration the budget (I think you mean Bill of Lading, which is a list of items)

??? (someone) reviews the bill of lading from CRS staff and makes any necessary changes

??? (someone) creates 15 photocopies of the tender

  
Not Ranked
Joined on Sun, Sep 3 2006
Florida - U.S.
New Member (18)
Actually, I know American English.
AddThis Feed Button RSS Feed: ESL, Business and Finance English
© 2008 MediaCET Ltd.
Terms and Conditions & Terms of Service